Parker Pioneer Stocks Orchids & Onions Obituaries Calendar Weather Public Notices Archives Clip n' Save Coupons
Weather Magnet

Faithful+Gould drops out of sewer project

By NATHAN BRUTTELL
Today's News-Herald
Published Wednesday, October 28, 2009 8:52 PM MST

City staff investigation into several sewer project proposals has led one engineering firm to drop out of projects.


Faithful+Gould, originally contracted Sept. 29 to complete about $65,000 of work on the sewer project, will no longer complete the work and will instead consider submitting qualifications for future work, it was announced Tuesday night during the City Council’s regular meeting. Problems arose when proposals started arriving that showed a $35,000 difference in estimated work than what was originally contracted.

Interim City Manager Charlie Cassens decided last week the issue needed City Council attention and consulted with Interim Public Works Director Mark Clark.

“We did this as an effort to clear out some of the controversy that essentially led to the meeting where Richard Kaffenberger was dismissed,” Cassens said. “ It became apparent that Faithful+Gould’s offers to do items of work was changing over time.”

The council had originally approved the contract for Faithful+Gould for a full system model audit, Sweetwater/Hagen Pump Station concept review and design review after former City Manager Richard Kaffenberger split the sewer project costs between the company and AMEC. Cassens said following the Sept. 29 meeting, Faithful+Gould came back and changed their projections a few times and finally indicated the work could not be done for the contract allotted.

“We then received another letter from Faithful+Gould that indicated they were interested in including oversight into the (request for qualifications) process and would participate in that way. It was them saying ‘Never mind about all the stuff we gave you before.’ Basically they wanted a chance to start over with other bidders.”

Cassens said he could not speculate as to the reasons for the constant proposal changes.

“I don’t want to accuse anybody of anything or suggest any wrongdoing. I just wanted to clear the air,” he said. “There was a whirlwind of information going on swirling around the city manager’s involvement and ... suggestions that there were design flaws and problems ... so we wanted to look back in time and figure it out.”

The modeling audit had no changes but on Oct. 2, Faithful+Gould submitted a proposal for the Sweetwater/Hagen concept review that saw a jump in estimates.

“They came back and said the cost would be $23,540,” Clark said. “They were originally given about $5,000 for that.”

Clark said the design plan review also had a significant change.

“A further submittal on Oct. 12 for the … design plan review was about $47,000 which was originally indicated at $18,000,” he said. “That’s what caused it to be an issue.”

City Council indicated Tuesday that engineering and construction firm PBS&J would take over the concept and design review for “significantly less” than Faithful+Gould’s proposals. PBS&J was previously approved to do design and expansion work through a bid process, Clark said.

“Still issues to be addressed with some design and modeling information,” Clark said. “Staff is confident that it will be worked out and these things don’t have impact on projects we’re doing now.”

Mayor Mark Nexsen said he felt the design review would be important to the city.

“I’m still a strong believer … only because questions have been raised, and I think they need an answer,” Nexsen said. “So to me it’s money well spent to dispel the issues that might be out there.”

City staff also released a proposed schedule for bid awards and construction dates for the sewer project. The plans call for the Trotwood area to be the last section, with bids awarded on March 23, 2010 and construction to take place from April 2010 to 2011.

You may contact the reporter at nbruttell@havasunews.com.

Article Rating

    Current Rating: 0 of 0 votes!Rate File:

Comments (2 comment(s))

    BonHomme Richard wrote on Oct 29, 2009 12:47 PM:

    " Let me see....Kaffenberger rips off the the city then is fired,Now the GOOD-O-BOYS cover for his then pays off Kaffenberger 160,000 dollars to end his contract? It looks to me that Fired doesn't let him draw the rest of his wadges....

    How deep do the crooks go in the city? "

    Had it with Havasu wrote on Oct 28, 2009 10:02 PM:

    " Without Kaffenberger to slide the cash through the system we're seeing the cash change hands. How about that? I'm sorry Mayor Nexsen, can you speak a little louder. "Money well spent...". Not a single dime going into this project has been well spent. It has been a disaster from day one and will continue to be for the foreseeable future. No review or study or analysis is going to change that.

    We need reality. We need to show the fundamental errors and the flawed engineering and the substandard construction. We need to go after bonds and fix this while we can do it without spending our money a second time. "

WRITE A COMMENT

Comment posters are responsible for the opinions they express and the accuracy of the information they provide. We urge comment writers to treat this as a public forum where manners matter. We encourage a collegial, non-insulting tone and we reserve the right to withhold or remove any comment from publication.

Do not post:
    * Potentially libelous statements or damaging innuendo.
    * Obscene, explicit, or racist language.
    * Personal attacks, insults or threats.
    * The use of another person's real name to disguise your identity.
    * Comments unrelated to the story.


Opinions, advice and all other information expressed in havasunews.com's story comments represent the individual's own views and not necessarily those of Today's News Herald. Today's News Herald provides an interactive computer service and does not endorse and is not responsible for statements, advice or opinions offered by anyone other than authorized Today's News Herald spokespersons.

Thank you for your comments!

You must register with a valid email to post comments. Only your Member ID will be posted with the comments.

Registered users sign in here:

Become a Registered User

*Member ID:
*Password:
Remember login?
(requires cookies)
 

Do not use usernames or passwords from your financial accounts!

Note: Fields marked with an asterisk (*) are required!

*Create a Member ID:
*Choose a password:
*Re-enter password:
*E-mail Address:
*Year of Birth:
 

(children under 13 cannot register)

*First Name:
*Last Name:
*Zip Code:
 
e-Edition

VIDEOS

American Profile

e-Edition

e-Edition

Special Sections








View All Special Sections

Readers' Poll

Calendar

Stocks